Wednesday, October 19, 2011

It's been a pretty exciting week! Rooms are beginning to form in DDBC house 6. We now have multiple shaded spaces for us to escape the beating sun..unless we are on the roof of course. We now have all our joists up in the kitchen and family room and the sheathing for the roof above it is being put in now. Rammed earth is progressing and we are a little over 60% done with our rammed earth walls!  



Framers and Rammed Earthers working side by side!  :) In this image above you can see the formwork for the rammed earth wall in one of the bedrooms and to the left of it is the living room and kitchen.


Joists above the kitchen.


All hands on deck! Here is the east wall of the living room.




Alan putting in the sheathing above the living room.

1 comment:

  1. i love when we all have to help place a wall up. its like an old fashioned barn raising. haha